Step 3 — Rebuilding

Start rebuilding

Permits in the right order, a realistic timeline, and the costs insurers tend to miss. The first step does not wait on your settlement.

What do I need to do before I can rebuild?

You can't start construction without permits, and there are steps that have to happen in order. The good news: Spokane has cut fees and is fast-tracking rebuilds.

1

Get an asbestos survey

Required before any demolition or building permit. A certified inspector tests your site. If negative, you can remove debris yourself. If positive, a WA Certified Asbestos Abatement Company handles removal, and contaminated debris goes to Graham Road Landfill.

Your contractor should be handling this conversation, not leaving it to you.

2

File a Notice of Intent with SRCAA

File online with the Spokane Regional Clean Air Agency. Can be done by you or your contractor. NOI fees are currently waived for fire-affected properties.

3

Get a demolition & cleanup permit

Fee reduced to $35 (normally up to $450). Processing and technology fees waived.

4

Apply for your rebuild permit

Same-footprint rebuilds are being targeted at 5–7 business days. If your original approved plans are on file, the permit office may be able to transfer them — one rebuild permit was issued in just two days (August 27, 2026).

A different size or layout needs full plan review, an architect, and possibly engineering. Budget additional weeks. A "like-for-like" code to speed same-footprint reviews further is under consideration.

Inside Spokane city limits

Development Services Center

WUI code in effect since June 12, 2024

Unincorporated county

Building & Planning · 509-477-3675

State code with local amendments — confirm before accepting an estimate

What your contractor should handle: the asbestos survey, the NOI, pulling the permits, and coordinating with the permit office. You shouldn't be managing this paperwork yourself.

Three things first estimates leave out

  • Well. Heat damage to the casing, pump and wiring is common, and a replacement is its own line item.
  • Septic. Tanks and drainfields get crushed by heavy equipment during debris removal, and the repair surfaces late.
  • Driveway and access. Culverts, gates and the driveway itself take the weight of demolition traffic. Rebuilding needs the access to work.

How long will this actually take?

A full rebuild typically takes 12–18 months from start to move-in. Some phases overlap — knowing which ones saves months.

Insurance claim & settlement

Ongoing

File your claim, get your own rebuild estimate, negotiate with your adjuster.

Runs in parallel with everything else — don't wait for settlement to start the steps below.

Asbestos survey & debris removal

2–6 weeks

Survey, NOI filing, demolition permit, and site clearance.

Start the asbestos survey while your claim is still in process.

Permits

1–4 weeks

Same-footprint rebuilds are being fast-tracked. New designs take longer.

Design & planning

4–8 weeks

If rebuilding to the same plans, this is short or skipped. New designs need an architect.

Can overlap with permitting if your builder coordinates it.

Construction

6–12 months

Foundation through final inspection. Weather, complexity, and material lead times all factor in.

Where insurance estimates and contractor estimates diverge

An adjuster's estimate and a contractor's estimate for the same house rarely land in the same place. Here's where the gaps typically show up.

Interior finishes

Usually includedGrade may be set lower than what was lost

Debris removal & haul-off

SometimesAsbestos abatement, disposal fees, landfill routing

Code upgrades (WUI materials, egress, insulation)

RarelyCovered under Ordinance & Law, often omitted

Permits & fees

SometimesPlan review, impact fees, SRCAA filings

Site work

RarelyFoundation inspection, erosion control, re-grading

Temporary utilities during construction

RarelyPower, water, portable sanitation

Utility reconnection (well, septic, meter reset)

Rarely

General conditions

SometimesSupervision, dumpsters, site security

Contractor overhead & profit

SometimesFrequently omitted or set below market

Landscaping & hardscape

RarelyFencing, driveway, retaining walls

Detached structures (garage, shed)

Separate limitOften overlooked entirely

None of this means your insurer is acting in bad faith. Adjusters work from software templates; builders work from actual local subcontractor pricing. The two rarely land in the same place on the first pass.

Not sure where your coverage stands?

The 2-minute coverage check gives you your own numbers to work from.